SpecTips - How to Add Insulation on a Roof when Space is Limited

5x the value of typical roof insulation

Adding insulation (R-value) in re-roofing applications can be challenging due to insulation height constraints.Low parapet and curb heights, through-wall scuppers, and penthouse doors and windows close to the roof’s surface can make it nearly impossible to add insulation without making significant modifications to the building. Building modifications are time-consuming and costly, requiring additional labor and materials.

OPTIM-R Vacuum Insulated Panels(VIPs)provide an R-38 insulating value in a 2.6” total system thickness. This unique solution is ideal for re-roofing projects with insulation space constraints. OPTIM-R eliminates the need for expensive building modifications during re-roofing by providing the highest R-value in the thinnest profile.Ithas up to five times the R-value of other commonly used roofing insulation products. Utilize OPTIM-R on your next project to efficiently add code-required or building owner-desired R-value.

3-Part Specification
  • Insulation –High-performance rigid vacuum insulated panels, sealed in gas-tight envelope, 1-9/16” minimum overall thickness as needed to achieve the required R-value for the roof, and the following characteristics:
    1.Minimum compressive strength = 23 lb/in2
    2.Board size = Nominal 1 9/16” (40mm) thick to achieve R-30 (length and width as required for optimized installation
    3.Minimum thermal resistance (aged R-value per inch) = 20.6B.
  • Manufacturer –Provide Kingspan OPTIM-R brand insulation or approved equal.
For more information, visit the product data sheet.

Up Next

August 05, 2020

30-Year EPDM Systems - Resilient by Design

One of the major themes in commercial construction is resilient design, which helps to keep buildings functional during and after severe weather events.

July 15, 2020

Jobsite Delivery, Storage, and Handling

Building products are sometimes delivered to the jobsite days or weeks before they are finally ready to be installed. While they are on the jobsite, what are some of the “best practices” a contractor should follow with regards to handling these products before use?